Azizi’s Beach Oasis II nears 62% completion in Dubai Studio City

Render of Beach Oasis II, Azizi Developments’ low-rise residential community in Dubai Studio City, seen from a landscaped streetRender of Beach Oasis II, the Azizi Developments community in Dubai Studio City where construction is close to 62% complete (Image source: Azizi Developments)

Dubai, UAE - Azizi Developments has reported that construction of Beach Oasis II, its mixed-use community in Dubai Studio City, is close to 62% complete, with site work now moving through MEP, plastering and interior finishes.

The Emirati developer is building 694 homes at the scheme, made up of around 452 studios, 209 one-bedroom units and 33 two-bedroom units.

A large swimming pool designed to resemble a beach will sit at the centre of the community’s courtyard. Azizi said residents will also have fully equipped gyms, landscaped gardens, children’s play areas and a central square with shops built into it.

On site, the development’s framework is now 100% complete, according to the developer. Blockwork stands at 99%, and internal plastering has climbed to 77%.

HVAC installation has reached 59% and MEP installation 50%. Finishes across the project are at 48%.

Work on the swimming pool is 38% done. Lift installation is at 34%, while façade works are at 15%.

Farhad Azizi, Group CEO of Azizi Developments, said: “With the core structural works behind us, our focus has now shifted to MEP routing, plastering, and the interior finishes that actually make these spaces livable. It’s a precise, detail-oriented phase of construction, and it keeps our momentum exactly where it needs to be as we push toward the final handover.”

The community sits on Hessa Street, close to Sheikh Mohammed Bin Zayed Road. Azizi describes the Dubai Studio City plot as well connected by road, with quick access to commercial, leisure and sports destinations and a direct route into the city centre.

Nearby attractions named by the developer include Dubai Autodrome, The Els Club, Dubai Polo & Equestrian Club, Dubai International Stadium and Dubai Miracle Garden. Schools and healthcare facilities are also in the area, Azizi said.

Progress has picked up since April, when Azizi put Beach Oasis II at 43% complete. At that stage the structure was 99% finished, blockwork was at 64%, internal plastering at 37%, HVAC at 21% and MEP at 31%.

The project follows Azizi’s original Beach Oasis, which was nearing 94% completion in August 2025, with handover scheduled for Q3 2025.