Abu Dhabi, UAE - Work has started on ADNOC Gas’ second Rich Gas Development (RGD) phase, after Wison Engineering held a groundbreaking on 11 November 2026 for the new natural gas processing train it is building at the ADNOC Gas Habshan site.
In August 2026, the gas processor awarded Wison Engineering the $3.9 billion engineering, procurement and construction (EPC) package on RGD Phase 2. With a related 220kV switch station included, the deal is worth approximately $4.04 billion in total, the biggest EPC job the contractor has taken on.
The train will be a large-scale addition to Habshan. Wison Engineering said that once it is complete, ADNOC Gas will have more processing capacity and more flexibility in operations, helping the UAE’s downstream and petrochemical industries keep developing.
As main contractor, Wison Engineering said it will bring its integrated EPC capability, strong execution and worldwide supply-chain resources to the train. The scope takes in the key gas treatment units and the deep natural gas liquids (NGL) recovery facilities.