TAQA consortium reaches $2.11bn financial close on Taweelah C power plant

Senior debt from local and international banks will fund most of the 2.6GW gas-fired Taweelah C plant, which TAQA is developing with Aljomaih and Sembcorp for EWEC.
Aerial view of the existing Taweelah power and water complex in Abu Dhabi, with pipework and steel structures and the sea behind, at the site where the 2.6GW Taweelah C gas-fired plant is to be builtAerial view of the existing Taweelah power and water complex in Abu Dhabi, with pipework and steel structures and the sea behind, at the site where the 2.6GW Taweelah C gas-fired plant is to be built. (Image source: TAQA)

Abu Dhabi, UAE - Funding is now in place for Taweelah C, a $2.11 billion (AED 7.76 billion) gas-fired independent power plant in Abu Dhabi, after the project reached financial close.

Offtaker Emirates Water and Electricity Company (EWEC) announced the milestone with lead developer Abu Dhabi National Energy Company (TAQA) and its partners, Aljomaih Energy and Water Company of Saudi Arabia and Sembcorp Industries of Singapore. The plant is meant to serve electricity demand that is rising with population growth, urban development and the spread of artificial intelligence data centres.

With a capacity of 2.6 gigawatts (GW), the high-efficiency plant is scheduled to enter commercial operation in 2029. It will provide flexible generation to help Abu Dhabi bring more renewable energy onto its grid, and its design allows carbon capture technologies to be added in future.

Most of the money comes as senior debt from local and international lenders: First Abu Dhabi Bank, HSBC, DBS, OCBC, Industrial and Commercial Bank of China and KfW International Project and Export Finance Bank.

Abu Dhabi Islamic Bank and Dubai Islamic Bank joined them in coordinating and arranging the deal.

The close comes after EWEC, TAQA and the international consortium signed the plant’s power purchase agreement. When EWEC awarded the project in June, it said the agreement runs through to 2050. EWEC will buy the net electricity the plant generates.

TAQA owns 60% of the project company, and the consortium of Aljomaih Energy and Water Company and Sembcorp Industries holds the other 40%. The split is reversed in the operations and maintenance company, where TAQA will hold 40% and the consortium 60%.

The engineering, procurement and construction (EPC) contract went to China Energy Engineering Corporation. Siemens Energy said in June that it would supply the plant’s gas and steam turbines, with the SGT5-9000HL gas turbines and SST5-5000 steam turbines made in Berlin and Muelheim, Germany.

EWEC names rapid urbanisation, population growth and the data centre expansion that comes with the adoption of artificial intelligence among the main forces expected to push up power demand through 2050.

To cover that demand while cutting emissions, the utility is procuring more solar power. It forecasts photovoltaic capacity of 15.5GW by 2030 and more than 35GW by 2035.

Large amounts of solar on the network need flexible generating capacity to keep supply steady when renewable output rises and falls. Taweelah C is designed to supply that flexibility, offsetting intermittent renewable generation and keeping the grid stable.

Mohamed Almarzooqi, Chief Assets Officer of EWEC, said: “Taweelah C provides the essential operational agility required to balance intermittent renewable power, ensuring an uninterrupted supply for the Nation’s economy.”

Almarzooqi said the plant would support Abu Dhabi’s shift towards a generation system that relies more and more on large-scale solar. He added that its electricity tariff was among the most competitive in the region, though the companies did not disclose the figure.

Dr Frank Possmeier, Chief Investment Officer of TAQA, said preliminary construction at Taweelah C had already begun. He said the plant would deliver efficient, flexible gas-fired power and support TAQA’s plans to enlarge its global generation portfolio.

TAQA is targeting 150GW of gross power capacity by 2030, with 50GW of that from flexible gas-fired generation, and the 2.6GW Taweelah C plant will count towards the goal.

Aljomaih’s Chief Executive Officer, Adnan Abdulhadi Buhuligah, said the plant would add supply as electricity demand grows and would support a more resilient energy mix.

The partners expect the project to open key technical and operational roles to Emirati professionals in line with national workforce development efforts. The plant is due to begin commercial operations in 2029.